Cost-Benefit Analysis for Mining Projects – DGMS Exam Notes


                              Introduction

In mining, every decision — from opening a new seam to purchasing equipment — involves costs and benefits.
A Cost-Benefit Analysis (CBA) evaluates whether a project or investment is economically viable by comparing expected costs against anticipated returns. For DGMS exams (Management Paper – Financial Management section), understanding CBA, NPV, IRR, and Payback Period is crucial for answering both objective and descriptive questions.

🏗️ Importance of Cost-Benefit Analysis 

Mining projects require large capital investments, long gestation periods, and involve significant environmental and safety obligations.
CBA helps ensure that resources are used efficiently and that the project adds economic value.
🔹 Key Objectives:
  1. Evaluate project feasibility before investment.
  2. Compare alternative mining methods or technologies.
  3. Quantify environmental and safety impacts in monetary terms.
  4. Assist management in decision-making for expansion or closure.
  5. Comply with DGMS & MoEFCC requirements (for EIA/EMP approval).
🔹 Real-World Example:

When deciding between an opencast and underground method, management uses CBA to assess production cost, recovery rate, environmental impact, and payback time.

💰 Methods for Mining Projects 

 Cost-Benefit Analysis in mining includes financial evaluation techniques that measure project profitability over its life cycle. 

  🔸 1. Net Present Value (NPV)
  • Formula:
    NPV = Σ [(Cash Inflow – Cash Outflow) / (1 + r)ⁿ]
  • A project is accepted if NPV > 0.
  • Reflects the present value of future cash flows discounted at rate r.
🔸 2. Benefit-Cost Ratio (BCR)
  • Formula:
    BCR = Present Value of Benefits / Present Value of Costs
  • Accept project if BCR > 1.0.
  • Used in public and environmental projects (like reclamation or R&R).
🔸 3. Payback Period (PBP)
  • Time taken to recover initial investment.
  • Shorter payback = better liquidity.
  • Simple but ignores time value of money.
🔸 4. Internal Rate of Return (IRR)
  • The discount rate at which NPV = 0.
  • Higher IRR = better project.
  • DGMS often tests formula interpretation for IRR-based questions.
🔸 5. Sensitivity Analysis
  • Measures impact of uncertainty (price change, cost escalation, delay).
  • Helps assess project risk under variable conditions.
🔸 6. Environmental & Social Costs
  • Includes rehabilitation, pollution control, afforestation, compensation, etc.
  • Must be factored into CBA for realistic decision-making.

📊 DGMS Exam Relevance 

 In DGMS exams, Cost-Benefit Analysis questions appear under:
  • Management & Legislation Paper
  • Financial Management sub-topic
  • Often linked with Payback Period, IRR, NPV, and Break-Even Analysis


Quick One-Liners
  • CBA compares project costs vs expected benefits.
  • NPV > 0 → Project acceptable.
  • BCR > 1 → Project viable.
  • Payback period → Time to recover investment.
  • IRR = rate where NPV = 0.
  • Environmental costs must be included.
  • Used for feasibility, expansion, or closure.
  • DGMS links it with Financial Management syllabus.
  • Sensitivity analysis measures risk.
  • DGMS may ask numeric examples in viva.


In mining, where investments are high and risks significant, CBA ensures decisions are economically and ethically justified. 

                           Conclusion:
For DGMS exam purposes, understanding and applying CBA principles are essential for evaluating the financial health and sustainability of mining operations.

🎯 25 MCQs – Cost-Benefit Analysis in Mining 

 Q1. The primary objective of Cost-Benefit Analysis is to:
A. Control production
B. Evaluate project feasibility
C. Monitor workers
D. Supervise safety
E. Prepare reports
Answer: B.
Solution: CBA compares project costs and benefits to assess feasibility.

Q2. NPV stands for:
A. Net Price Value
B. Net Present Value
C. New Profit Variable
D. Net Project Value
E. None
Answer: B.
Solution: NPV = present value of future cash flows.

Q3. A project is accepted if NPV is:
A. Negative
B. Zero
C. Positive
D. Constant
E. None
Answer: C.
Solution: Positive NPV indicates profitability. Q4. BCR > 1 means:
A. Loss
B. Break-even
C. Profitable project
D. Rejected
E. None
Answer: C.
Solution: Benefit-Cost Ratio > 1 indicates feasibility.

Q5. IRR is the rate at which:
A. NPV = 0
B. Cost = Benefit
C. Profit = Loss
D. ROI = NPV
E. None
Answer: A.
Solution: Defines breakeven discount rate.

Q6. Payback Period indicates:
A. Project cost
B. Time to recover investment
C. NPV
D. Interest rate
E. None
Answer: B.
Solution: Measures liquidity and risk.

Q7. Shorter payback period means:
A. High risk
B. Low liquidity
C. Faster recovery
D. Longer ROI
E. None
Answer: C.
Solution: Indicates quicker return.

Q8. Sensitivity analysis is used to:
A. Estimate cost
B. Measure project risk
C. Reduce pollution
D. Design ventilation
E. None
Answer: B.
Solution: Tests project under uncertain conditions.

Q9. NPV calculation includes:
A. Cash inflows only
B. Cash outflows only
C. Both inflows and outflows
D. None
E. Current cost only
Answer: C.
Solution: Both inflows and outflows discounted. Q10. Discount rate in NPV represents:
A. Inflation rate
B. Cost of capital
C. Payback ratio
D. None
E. Profit margin
Answer: B.
Solution: Reflects company’s required rate of return.

Q11. CBA in mining helps:
A. Production planning
B. Financial decision-making
C. Safety audit
D. Manpower scheduling
E. None
Answer: B.
Solution: Supports investment decisions.

Q12. Environmental cost includes:
A. Compensation
B. Pollution control
C. Reclamation
D. All of the above
E. None
Answer: D.
Solution: All included in mining CBA.

Q13. IRR is useful for:
A. Small projects only
B. Comparing alternative investments
C. Annual reports
D. Budget allocation
E. None
Answer: B.
Solution: Helps compare project profitability. Q14. CBA used before:
A. Project execution
B. Closure
C. Training
D. Maintenance
E. None
Answer: A.
Solution: Conducted during feasibility stage. Q15. When BCR = 1, the project is:
A. Profitable
B. Neutral
C. Rejected
D. Unsafe
E. None
Answer: B.
Solution: Neither profit nor loss.

Q16. Environmental and social costs are known as:
A. Tangible
B. Intangible
C. Capital
D. Operational
E. None
Answer: B.
Solution: Often difficult to quantify.

Q17. DGMS syllabus includes CBA under:
A. Legislation
B. Management (Financial Management)
C. Safety
D. Ventilation
E. Environment
Answer: B.
Solution: Part of Financial Management.

Q18. IRR > Cost of Capital means:
A. Reject project
B. Accept project
C. Reduce investment
D. None
E. Delay approval
Answer: B.
Solution: Indicates profitability.

Q19. CBA in mining includes:
A. Production value
B. Equipment life
C. Social impact
D. All of the above
E. None
Answer: D.
Solution: Comprehensive evaluation.

Q20. Time value of money is ignored in:
A. IRR
B. NPV
C. Payback Period
D. BCR
E. None
Answer: C.
Solution: Payback ignores time value.

Q21. NPV is sensitive to:
A. Discount rate
B. Labour wages
C. Machinery cost
D. All of the above
E. None
Answer: D.
Solution: All influence NPV.

Q22. Positive NPV implies:
A. Cost > Benefit
B. Benefit > Cost
C. Equal
D. Unknown
E. None
Answer: B.
Solution: Indicates net gain.

Q23. DGMS evaluates project economics in:
A. Planning stage
B. Design stage
C. Both A & B
D. Closure stage
E. None
Answer: C.
Solution: Economic feasibility critical pre-approval.

Q24. Cash inflows in mining include:
A. Production revenue
B. Scrap sale
C. Subsidy
D. All of the above
E. None
Answer: D.
Solution: All inflows.

Q25. Cost-Benefit Analysis helps ensure:
A. Technical feasibility
B. Economic sustainability
C. Statutory compliance only
D. Safety plan
E. None
Answer: B.
Solution: Ensures long-term profitability.

 👉 Master project economics & cost-benefit analysis with OnlineMiningExam’s DGMS video lectures and mock tests.
Join India’s 1st Online Mining Academy to strengthen your financial management preparation today!


 



{{ONLINEMININGEXAM.COM}}
India's 1st Online Mining Academy Prepare for DGMS 1st Class & 2nd Class Mining Manager Exams (Coal & Metal, Restricted & Unrestricted)..

OUR COURSES View More