Cost-Benefit Analysis for Mining Projects – DGMS Exam Notes
Introduction
In mining, every decision — from opening a new seam to purchasing equipment — involves costs and benefits. A Cost-Benefit Analysis (CBA) evaluates whether a project or investment is economically viable by comparing expected costs against anticipated returns. For DGMS exams (Management Paper – Financial Management section), understanding CBA, NPV, IRR, and Payback Period is crucial for answering both objective and descriptive questions.
🏗️ Importance of Cost-Benefit Analysis
Mining projects require large capital investments, long gestation periods, and involve significant environmental and safety obligations. CBA helps ensure that resources are used efficiently and that the project adds economic value. 🔹 Key Objectives:
Evaluate project feasibility before investment.
Compare alternative mining methods or technologies.
Quantify environmental and safety impacts in monetary terms.
Assist management in decision-making for expansion or closure.
Comply with DGMS & MoEFCC requirements (for EIA/EMP approval).
🔹 Real-World Example:
When deciding between an opencast and underground method, management uses CBA to assess production cost, recovery rate, environmental impact, and payback time.
💰 Methods for Mining Projects
Cost-Benefit Analysis in mining includes financial evaluation techniques that measure project profitability over its life cycle.
Reflects the present value of future cash flows discounted at rate r.
🔸 2. Benefit-Cost Ratio (BCR)
Formula: BCR = Present Value of Benefits / Present Value of Costs
Accept project if BCR > 1.0.
Used in public and environmental projects (like reclamation or R&R).
🔸 3. Payback Period (PBP)
Time taken to recover initial investment.
Shorter payback = better liquidity.
Simple but ignores time value of money.
🔸 4. Internal Rate of Return (IRR)
The discount rate at which NPV = 0.
Higher IRR = better project.
DGMS often tests formula interpretation for IRR-based questions.
🔸 5. Sensitivity Analysis
Measures impact of uncertainty (price change, cost escalation, delay).
Helps assess project risk under variable conditions.
🔸 6. Environmental & Social Costs
Includes rehabilitation, pollution control, afforestation, compensation, etc.
Must be factored into CBA for realistic decision-making.
📊 DGMS Exam Relevance
In DGMS exams, Cost-Benefit Analysis questions appear under:
Management & Legislation Paper
Financial Management sub-topic
Often linked with Payback Period, IRR, NPV, and Break-Even Analysis
⚡ Quick One-Liners
CBA compares project costs vs expected benefits.
NPV > 0 → Project acceptable.
BCR > 1 → Project viable.
Payback period → Time to recover investment.
IRR = rate where NPV = 0.
Environmental costs must be included.
Used for feasibility, expansion, or closure.
DGMS links it with Financial Management syllabus.
Sensitivity analysis measures risk.
DGMS may ask numeric examples in viva.
In mining, where investments are high and risks significant, CBA ensures decisions are economically and ethically justified.
Conclusion: For DGMS exam purposes, understanding and applying CBA principles are essential for evaluating the financial health and sustainability of mining operations.
🎯 25 MCQs – Cost-Benefit Analysis in Mining
Q1. The primary objective of Cost-Benefit Analysis is to: A. Control production B. Evaluate project feasibility C. Monitor workers D. Supervise safety E. Prepare reports Answer: B. Solution: CBA compares project costs and benefits to assess feasibility.
Q2. NPV stands for: A. Net Price Value B. Net Present Value C. New Profit Variable D. Net Project Value E. None Answer: B. Solution: NPV = present value of future cash flows.
Q3. A project is accepted if NPV is: A. Negative B. Zero C. Positive D. Constant E. None Answer: C. Solution: Positive NPV indicates profitability. Q4. BCR > 1 means: A. Loss B. Break-even C. Profitable project D. Rejected E. None Answer: C. Solution: Benefit-Cost Ratio > 1 indicates feasibility.
Q5. IRR is the rate at which: A. NPV = 0 B. Cost = Benefit C. Profit = Loss D. ROI = NPV E. None Answer: A. Solution: Defines breakeven discount rate.
Q6. Payback Period indicates: A. Project cost B. Time to recover investment C. NPV D. Interest rate E. None Answer: B. Solution: Measures liquidity and risk.
Q7. Shorter payback period means: A. High risk B. Low liquidity C. Faster recovery D. Longer ROI E. None Answer: C. Solution: Indicates quicker return.
Q8. Sensitivity analysis is used to: A. Estimate cost B. Measure project risk C. Reduce pollution D. Design ventilation E. None Answer: B. Solution: Tests project under uncertain conditions.
Q9. NPV calculation includes: A. Cash inflows only B. Cash outflows only C. Both inflows and outflows D. None E. Current cost only Answer: C. Solution: Both inflows and outflows discounted. Q10. Discount rate in NPV represents: A. Inflation rate B. Cost of capital C. Payback ratio D. None E. Profit margin Answer: B. Solution: Reflects company’s required rate of return.
Q11. CBA in mining helps: A. Production planning B. Financial decision-making C. Safety audit D. Manpower scheduling E. None Answer: B. Solution: Supports investment decisions.
Q12. Environmental cost includes: A. Compensation B. Pollution control C. Reclamation D. All of the above E. None Answer: D. Solution: All included in mining CBA.
Q13. IRR is useful for: A. Small projects only B. Comparing alternative investments C. Annual reports D. Budget allocation E. None Answer: B. Solution: Helps compare project profitability. Q14. CBA used before: A. Project execution B. Closure C. Training D. Maintenance E. None Answer: A. Solution: Conducted during feasibility stage. Q15. When BCR = 1, the project is: A. Profitable B. Neutral C. Rejected D. Unsafe E. None Answer: B. Solution: Neither profit nor loss.
Q16. Environmental and social costs are known as: A. Tangible B. Intangible C. Capital D. Operational E. None Answer: B. Solution: Often difficult to quantify.
Q17. DGMS syllabus includes CBA under: A. Legislation B. Management (Financial Management) C. Safety D. Ventilation E. Environment Answer: B. Solution: Part of Financial Management.
Q18. IRR > Cost of Capital means: A. Reject project B. Accept project C. Reduce investment D. None E. Delay approval Answer: B. Solution: Indicates profitability.
Q19. CBA in mining includes: A. Production value B. Equipment life C. Social impact D. All of the above E. None Answer: D. Solution: Comprehensive evaluation.
Q20. Time value of money is ignored in: A. IRR B. NPV C. Payback Period D. BCR E. None Answer: C. Solution: Payback ignores time value.
Q21. NPV is sensitive to: A. Discount rate B. Labour wages C. Machinery cost D. All of the above E. None Answer: D. Solution: All influence NPV.
Q22. Positive NPV implies: A. Cost > Benefit B. Benefit > Cost C. Equal D. Unknown E. None Answer: B. Solution: Indicates net gain.
Q23. DGMS evaluates project economics in: A. Planning stage B. Design stage C. Both A & B D. Closure stage E. None Answer: C. Solution: Economic feasibility critical pre-approval.
Q24. Cash inflows in mining include: A. Production revenue B. Scrap sale C. Subsidy D. All of the above E. None Answer: D. Solution: All inflows.
Q25. Cost-Benefit Analysis helps ensure: A. Technical feasibility B. Economic sustainability C. Statutory compliance only D. Safety plan E. None Answer: B. Solution: Ensures long-term profitability.
👉 Master project economics & cost-benefit analysis with OnlineMiningExam’s DGMS video lectures and mock tests. Join India’s 1st Online Mining Academy to strengthen your financial management preparation today!